The experience of Motlima Consultores S.A. in the dam area includes the complete studies and projects to make arch dams, gravity dams, buttress dams, earth dams, rock fill dam, dikes and landfills, as well as the management and execution of Works.
Studies
• Energía Hidroeléctrica Andina
(Hidrandina)
Ancash, Pishcapaccha Valley.
Feasibility study and project at the work
execution level, of Pishcapaccha Earth Dam,
43 m-tall, with a capacity of 40 million m3
of water.
June 1981 – April 1983
• Electrolima S.A.
Lima, Huarochiri Province
Study of Feasibility and design at the
construction level of Yuracmayo earth
reservoir, 53 m-tall, with a capacity of
50 million m3 of water.
September 1981 – November 1984
Supervisions
• Electrolima
Lima, Santa Eulalia, Huarochiri Province.
Supervision and management of the
construction works and design of facilities
and complementary works during the
construction stage of the Huinco dam and
regulating reservoir. Dam of 215,000 m3
of reservoir, 25.5 m-tall and with an
elevation of 80 m.
1967 - 1970
• Electrolima S.A.
Lima, Santa Eulalia, Huarochiri Province
Supervision, management and start-up
of the construction of Sheque Reservoir.
Earth Dam of 430,000 m3 of reservoir
volume, 38.6 m-tall, and with an
elevation of 125 m.
1972 – 1975
• Moquegua Regional Government
Moquegua Region, General
Sanchez Cerro Province
Supervision of the construction of the
irrigation infrastructure, Chirimayuni Dam.
Capacity: 4.6 million m3 of water
2011