The experience of MOTLIMA Consultores S.A. in the tunnels field includes the supervision of large-scale water channeling tunnels which are intended for multiple purposes, such as irrigation improvement, the extension of the agricultural boundary, electric power generation and, finally, drinking water supply.

 

The hydraulic structures of these projects have been generally made up of: water intake, adduction system with tunnels, channels and pressure pipes, up to the point of use.

Supervisions

Empresa Nacional de Ferrocarriles

   S.A. ENAFER

   Lima- Central Train

    Work supervision: Quebrada La Esperanza

    Tunnel, over 777 m.

    December 1981 – June 1982.

 

Chavimochic Special Project

   La Libertad.

    Work Supervision: Intercuencas Tunnel

    Exit Chavimochic Project over 5,300 m

 

Pasto Grande Special Project

    Moquegua- District of Carumas,

    Mariscal Nieto Province

    Work Supervision. Jachacuesta Tunnel

    over 7,100 m.

    March 1990 – July 1994.

 

Special Project of Consolidation

   and Increase of the Water

   Resources of Tacna

    Tacna.

    Work Supervision. Trasandino Kovire

    Tunnel over 8,433 m.

   December 1990 – December 1995.

 

Proyecto Especial

   Chavimochic – INAE

    La Libertad, Province of Trujillo.

    Work Supervision: First stage, Package A,

    includes 7.7 Km of open channel and a

    capacity of 80 m3/sec, 2.7 km of open

    pipe and 18 km of tunnels.

    August 1988- September 1990.